F R 3 - 2 0 0 1 |
F-22 RAPTOR STRUGGLES TO MEET TARGETSBy Karl SchwarzIt should have been a merry Christmas for all those involved in the F-22 programme, but instead the festive season and the start of the new year turned out to be a hard slog. Because some critical test criteria explicitly required by Congress had not yet been satisfied, the US Department of Defense put back the planned 21 December meeting of the Defense Acquisition Board, first to 3 January and then to still further down the road. Now the new government under President George W. Bush, incumbent since 20 January, will have to turn his attention to LRIP approval for the stealth fighter, already delayed by a year. The change of government will not exactly make matters any easier, as it means that manufacturer Lockheed Martin and the US Air Force will now have to brief a new set of decision-makers on the programme details. Although it seems likely that total military expenditure will increase under Bush and his defense minister Donald Rumsfeld, the Raptor is unlikely to be given a blank cheque by the new administration. There are too many critical voices for this. In particular, the General Accounting Office (GAO) issued another warning last year that the costs could significantly exceed the strict limits imposed by Congress. The GAO, acting on behalf of Congress, pointed out that both the Air Force estimate of the cost of building 339 aircraft ($40.8 billion) and the Pentagon's forecast ($48.6 billion) exceed the $39.8 billion limit. The discrepancy of almost 20% arises from different calculation methods, but above all from different estimates as to whether planned cost reductions of no less than $21 billion can be implemented or not. Sample data has shown, according to the GAO, that a significant part of the savings programme is not actually under the control of the Air Force or the manufacturers. For example, orders running over a number of years require approval from Congress. One legitimate way out would of course be to reduce the number of aircraft to be purchased, but the USAF is already complaining that it will need additional F-22's in order to equip the squadrons for all its expeditionary air forces. In order to remain within the limits, the programme management team in Wright Patterson AFB, Ohio is resorting to all the tricks in the book. The latest idea is initially to ramp up the production rate more slowly in order to put money released into optimising production processes, which will make later aircraft cheaper to manufacture. Moreover, there are cost limits not just for production, but also for development and testing ($20.4 billion at 2000 prices). Here, costs are currently estimated to be around $200 million over budget. There are therefore apparently plans to initially forego qualification of certain equipment (helmet-mounted sight and AIM-9X Sidewinder). But even so the F-22 would still be able to satisfy its operational requirements according to the programme office. As well as the concerns about the costs, the test programme was causing headaches last year as well. Problems with fine cracks in the cockpit canopies, for example, led to the Raptor being grounded for almost four weeks in the spring. Then prototypes 4003 to 4006 were up to a year late in achieving flying condition. This meant that satisfying the dozen test items set by Congress became a race against time. Three of them the F-22 team only managed to clear in December and January 2001, while another two were still outstanding at the time of going to press (see box). All this suggests that the Raptor programme will continue to be an uphill struggle for Lockheed Martin and the Air Force. However, cancellation of the air-dominance fighter, as was menacingly hanging in the air in the middle of 1999, is very unlikely. Again, a delay in the decision to release $2.1 billion for the first ten production aircraft is currently not yet critical. As a precaution, the budget for 2001 allows $350 million to cover delay-free continuation of the programme to the end of March. Raptor tests item by itemIn response to pressure from the US Congress, the Pentagon (Undersecretary of Defense for Acquisition, Technology and Logistics) imposed 15 criteria which had to be satisfied before the first 10 serial production Raptors could be ordered. These concerned both the flight test programme and also ground testing and development milestones for the highly complex software. Specifically, the milestones are as follows:
From page 64 of FLUG REVUE 3/2001
Home | Update | LATEST ISSUE | Gallery | FR Inside | Datafiles | FR 3/2001 Copyright 2001 by Motor-Presse Stuttgart. All rights reserved. Last updated 3 February 2001 FLUG REVUE, Ubierstr. 83, 53173 Bonn, Germany |